Physical Plant Division Ongoing Projects

Projects Started in 2024

Repair and Renovation of Dir. Lucman's Cottage

Project Engineer Engr. Nomairy Sacar
Date Started June 1, 2024
% of Accomplishment 64%

Repair & Renovation of Sarangani's Cottage

Project Engineer Engr. Muhammad Salic Omar
Date Started April 3, 2024
% of Accomplishment 62%

Repair / Renovation of Ceramic’s Office And Tiling of Director’s Office

Project Engineer Engr. Nomairy Sacar
Date Started May 20, 2024
% of Accomplishment 95%

Repair/Concreting of Display Cabinets for BioChem Bldg.

Project Engineer TBD
Date Started TBD
% of Accomplishment TBD

Replacement of Ceiling Bio Chem Bldg. 2nd Floor

Project Engineer Engr. Sittie Naida Grande-Isra
Date Started TBD
% of Accomplishment 78%

Replacement of Ceiling Bio Chem Bldg. Ground Floor

Project Engineer Engr. Sittie Naida Grande-Isra
Date Started TBD
% of Accomplishment 95%

Repair/Renovation of Cottage #1

Project Architect Arch. Josefus Fortuna
Date Started TBD
% of Accomplishment 87%

Perimeter fence of IT Hub Bldg. (with gate)

Project Engineer Engr. Muhammad Omar Salic
Date Started March 21, 2024
% of Accomplishment 89%

Repair / Renovation of BQ #1

Project Engineer Engr. Aiman M. Billy
Date Started July 1, 2024
% of Accomplishment 30%

Repair / Renovation of Comfort Room at Rajah Solaiman Hall Dormitory

Project Engineer Engr. Mustapha Abedin
Estimated By Engr. Muhammad Omar Salic
Date Started TBD
% of Accomplishment 68%

Projects Started in 2023

Repair / Renovation of Comfort Room at Rajah Dumduma Hall

Project Engineer Engr. Hanifa Paunte
Date Started June 10, 2023
% of Accomplishment 98%